We hope you enjoy the latest construction update for Fable by Rogerscorp
Over the past month we’ve seen some incredible progress onsite with several significant milestones reached. The framing for residences 39-42, 44, 46, 48, 56, and 57 has been erected, marking a significant step forward.
Roofing installation is complete for residences 1-10 and 31-38, with cladding currently underway. Residences 11-30 have also seen substantial progress, with exterior cladding complete and scaffolding removed. Interior painting and joinery installation is 60% complete, with the remaining residences following closely behind.
Foundations have been installed for residences 43, 45, 47, 49, and 51. Service rough-ins have been completed for residences 1-10, 14, 16, 18, and 26-30, ensuring essential utilities are in place. Additionally, linings and interior finishes are rapidly progressing in residences 2, 4, 6, 8, 10, 11, 14, 16, 18, and 23-25.
We’re now starting to see the private amenities take shape with concrete slabs being poured and the pool shell now in place. It’s been a busy few weeks at Fable, and we look forward to sharing more progress in the coming months.
Publisher:
Rogerscorp
PROJECT NEWS
Fable by Rogerscorp - Construction Update May 2024